Question

What are the limitations of using data from earlier projects to estimate the cost of a new project?

a.

The new project must resemble old projects

b.

The new project must be of the same kind and within the same organization as the old projects

c.

The model based on data from one organization cannot be used in a different organization

d.

All of the above

Posted under Software Engineering

Answer: (d).All of the above Explanation:The limitations of using data from earlier projects to estimate the cost of a new project are that the new project must resemble old projects, the new project must be of the same kind and within the same organization as the old projects and the model based on data from one organization cannot be used in a different organization.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What are the limitations of using data from earlier projects to estimate the cost of a new project?

Similar Questions

Discover Related MCQs

Q. What are some of the limitations of using real project data to arrive at cost estimation models?

Q. What is one of the reasons why the models of Walston and Felix and Boehm yield different results for one and the same problem description?

Q. What are some of the factors that are taken into account while collecting data for cost estimation models?

Q. What is the main determinant of effort and cost in software development?

Q. What is one of the strategies for improving software productivity?

Q. What can be done to get the best from people in software development?

Q. What is one of the reasons for rework in software development?

Q. What can integrated project support environments do to improve software development?

Q. What are some of the common characteristics of various cost estimation models?

Q. What are some of the reasons for the discrepancies between existing cost estimation models?

Q. What is the main disadvantage of expert-based cost estimation?

Q. Why are algorithmic models not suitable for agile projects?

Q. What is the main disadvantage of shortening the nominal development time?

Q. What is the general form of the equation used to express the correlation between programming effort and program size in algorithmic models?

Q. What is the primary cost driver in algorithmic models for software cost estimation?

Q. In algorithmic models, what is the value of "c" in the equation E=(a+bKLOC)f(x1;:;xn)?

Q. What is the primary cost driver in software development projects?

Q. What is the difference between the Walston-Felix model and the Boehm-Halstead model?

Q. What is the economy of scale?

Q. What is the value of the exponent in the software cost estimation models?