Question

What is one of the strategies for improving software productivity?

a.

Writing more code

b.

Hiring less qualified personnel

c.

Not using high-level languages

d.

Writing less code

Posted under Software Engineering

Answer: (d).Writing less code Explanation:One of the strategies for improving software productivity is to write less code by using techniques such as software reuse and high-level languages.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is one of the strategies for improving software productivity?

Similar Questions

Discover Related MCQs

Q. What can be done to get the best from people in software development?

Q. What is one of the reasons for rework in software development?

Q. What can integrated project support environments do to improve software development?

Q. What are some of the common characteristics of various cost estimation models?

Q. What are some of the reasons for the discrepancies between existing cost estimation models?

Q. What is the main disadvantage of expert-based cost estimation?

Q. Why are algorithmic models not suitable for agile projects?

Q. What is the main disadvantage of shortening the nominal development time?

Q. What is the general form of the equation used to express the correlation between programming effort and program size in algorithmic models?

Q. What is the primary cost driver in algorithmic models for software cost estimation?

Q. In algorithmic models, what is the value of "c" in the equation E=(a+bKLOC)f(x1;:;xn)?

Q. What is the primary cost driver in software development projects?

Q. What is the difference between the Walston-Felix model and the Boehm-Halstead model?

Q. What is the economy of scale?

Q. What is the value of the exponent in the software cost estimation models?

Q. What is the problem with using lines of code as a measure for software size in cost estimation?

Q. What is the solution to the problem of unreliable software size estimates early on in a project?

Q. What is the main problem with existing algorithmic models for cost estimation?

Q. What is the base equation of Walston and Felix's model?

Q. How many factors does the Walston and Felix model consider?