In algorithmic models, what is the value of "c" in the equation E=(a+bKLOC)f(x1;:;xn)?

a.

A constant value

b.

A correction factor based on the values of x1 to xn

c.

A variable value based on the programming team's experience

d.

A value that fluctuates around 1

Answer: (d).A value that fluctuates around 1 Explanation:In algorithmic models, the value of "f" in the equation E=(a+bKLOC)f(x1;:;xn) fluctuates around the value of 1. This is based on the available project data and the various factors that influence productivity.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. In algorithmic models, what is the value of "c" in the equation E=(a+bKLOC)f(x1;:;xn)?

Similar Questions

Discover Related MCQs

Q. What is the primary cost driver in software development projects?

Q. What is the difference between the Walston-Felix model and the Boehm-Halstead model?

Q. What is the economy of scale?

Q. What is the value of the exponent in the software cost estimation models?

Q. What is the problem with using lines of code as a measure for software size in cost estimation?

Q. What is the solution to the problem of unreliable software size estimates early on in a project?

Q. What is the main problem with existing algorithmic models for cost estimation?

Q. What is the base equation of Walston and Felix's model?

Q. How many factors does the Walston and Felix model consider?

Q. What are the values that the variables Xi can take on in the Walston and Felix model?

Q. What is the approach taken by Walston and Felix for their model?

Q. What is the reason for the wide-ranging results obtained by Walston and Felix's model?

Q. What are the three classes of project that COCOMO model distinguishes?

Q. What is the formula that relates effort to software size in Basic COCOMO?

Q. What is the value of b for organic projects in COCOMO?

Q. How does the constant 'c' impact the estimate obtained in COCOMO model?

Q. How accurate are the results of the Basic COCOMO model?

Q. How does the Intermediate COCOMO model compare to the Basic COCOMO model in terms of accuracy?

Q. What is a major advantage of COCOMO?

Q. Which of the following is not a class of project in COCOMO?