What is a limitation of laboratory experiments used to determine the equations of a cost estimation model?

a.

They are not representative of industrial settings

b.

They are not limited in size

c.

They do not consider market trends

d.

They do not account for holidays and sick-leave

Posted under Software Engineering

Answer: (a).They are not representative of industrial settings Explanation:Laboratory experiments are often performed at universities with students as subjects and may not be representative of the conditions and professionals encountered in industrial settings.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is a limitation of laboratory experiments used to determine the equations of a cost estimation model?

Similar Questions

Discover Related MCQs

Q. What is the main problem with comparing different cost estimation models?

Q. What is the typical approach for determining the equations of an algorithmic cost estimation model?

Q. What is one of the assumptions that is typically made in laboratory experiments to determine cost estimation models?

Q. What are the two ways to arrive at algorithmic cost estimation models?

Q. What are the limitations of using the results from laboratory experiments in cost estimation models?

Q. What are the limitations of using data from earlier projects to estimate the cost of a new project?

Q. What are some of the limitations of using real project data to arrive at cost estimation models?

Q. What is one of the reasons why the models of Walston and Felix and Boehm yield different results for one and the same problem description?

Q. What are some of the factors that are taken into account while collecting data for cost estimation models?

Q. What is the main determinant of effort and cost in software development?

Q. What is one of the strategies for improving software productivity?

Q. What can be done to get the best from people in software development?

Q. What is one of the reasons for rework in software development?

Q. What can integrated project support environments do to improve software development?

Q. What are some of the common characteristics of various cost estimation models?

Q. What are some of the reasons for the discrepancies between existing cost estimation models?

Q. What is the main disadvantage of expert-based cost estimation?

Q. Why are algorithmic models not suitable for agile projects?

Q. What is the main disadvantage of shortening the nominal development time?

Q. What is the general form of the equation used to express the correlation between programming effort and program size in algorithmic models?