Question

What is the main problem with comparing different cost estimation models?

a.

They use different measures and cost drivers

b.

They are difficult to understand

c.

They are not well-established

d.

They are not applicable in industrial settings

Posted under Software Engineering

Answer: (a).They use different measures and cost drivers Explanation:Different models use different measures and cost drivers, making it difficult to compare results and draw accurate conclusions.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the main problem with comparing different cost estimation models?

Similar Questions

Discover Related MCQs

Q. What is the typical approach for determining the equations of an algorithmic cost estimation model?

Q. What is one of the assumptions that is typically made in laboratory experiments to determine cost estimation models?

Q. What are the two ways to arrive at algorithmic cost estimation models?

Q. What are the limitations of using the results from laboratory experiments in cost estimation models?

Q. What are the limitations of using data from earlier projects to estimate the cost of a new project?

Q. What are some of the limitations of using real project data to arrive at cost estimation models?

Q. What is one of the reasons why the models of Walston and Felix and Boehm yield different results for one and the same problem description?

Q. What are some of the factors that are taken into account while collecting data for cost estimation models?

Q. What is the main determinant of effort and cost in software development?

Q. What is one of the strategies for improving software productivity?

Q. What can be done to get the best from people in software development?

Q. What is one of the reasons for rework in software development?

Q. What can integrated project support environments do to improve software development?

Q. What are some of the common characteristics of various cost estimation models?

Q. What are some of the reasons for the discrepancies between existing cost estimation models?

Q. What is the main disadvantage of expert-based cost estimation?

Q. Why are algorithmic models not suitable for agile projects?

Q. What is the main disadvantage of shortening the nominal development time?

Q. What is the general form of the equation used to express the correlation between programming effort and program size in algorithmic models?

Q. What is the primary cost driver in algorithmic models for software cost estimation?