Question

What approach is suitable for software development projects with fixed and stable requirements?

a.

A tightly structured approach

b.

An agile approach

c.

A risk management approach

d.

A project schedule approach

Answer: (a).A tightly structured approach Explanation:If the developing organization has considerable experience with the application domain and the requirements are fixed and stable, a tightly structured approach may yield a satisfactory solution.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What approach is suitable for software development projects with fixed and stable requirements?

Similar Questions

Discover Related MCQs

Q. What is the purpose of considering project control from a systems point of view?

Q. What are irregular variables?

Q. What are the sources of information that guide the decision process?

Q. What are goal variables?

Q. What is the role of the project manager in the system of project control?

Q. What is an important precondition for effective control in software development projects?

Q. What are some conflicting goals that can be distinguished in software development projects?

Q. What are goal variables in a software development project?

Q. What are control variables in a software development project?

Q. What are some examples of possible control variables in a software development project?

Q. What are the conditions for effective control of a system in systems theory?

Q. How does the degree of control in a software development project increase?

Q. What is necessary to measure both the project and the product in software development?

Q. What does controlling software development imply?

Q. How is controlling a software development project described in practice?

Q. What are the three classes of project characteristics that are important for project control?

Q. How does the degree of certainty of product characteristics affect project control?

Q. Which project characteristics are important for project control in software development?

Q. How does control differ in projects with high product certainty compared to low product certainty?

Q. What are the characteristics that are common to most or all software development projects?