adplus-dvertising

Welcome to the Systems Analysis and Design Methods Basics MCQs Page

Dive deep into the fascinating world of Systems Analysis and Design Methods Basics with our comprehensive set of Multiple-Choice Questions (MCQs). This page is dedicated to exploring the fundamental concepts and intricacies of Systems Analysis and Design Methods Basics, a crucial aspect of Systems Analysis and Design Methods. In this section, you will encounter a diverse range of MCQs that cover various aspects of Systems Analysis and Design Methods Basics, from the basic principles to advanced topics. Each question is thoughtfully crafted to challenge your knowledge and deepen your understanding of this critical subcategory within Systems Analysis and Design Methods.

frame-decoration

Check out the MCQs below to embark on an enriching journey through Systems Analysis and Design Methods Basics. Test your knowledge, expand your horizons, and solidify your grasp on this vital area of Systems Analysis and Design Methods.

Note: Each MCQ comes with multiple answer choices. Select the most appropriate option and test your understanding of Systems Analysis and Design Methods Basics. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

Systems Analysis and Design Methods Basics MCQs | Page 1 of 19

Explore more Topics under Systems Analysis and Design Methods

Q1.
A task of developing a technical blueprint and specifications for a solution that fulfills the business requirements is undertaken in the following phase of the system development process
Discuss
Answer: (d).system design
Discuss
Answer: (d).the activity of documenting, managing, and continually improving the process of systems development
Q3.
From a project management perspective, a project is considered a success if
Discuss
Answer: (d).all of the above
Discuss
Answer: (b).lack of project documentation
Q5.
Which one is NOT a project management activity?
Discuss
Answer: (d).assess risks
Q6.
Which of the following is a graphical network model that depicts a project’s tasks and the relationships between those tasks?
Discuss
Answer: (a).PERT chart
Q7.
An inter-task dependency in which two tasks must finish at the same time is referred to as
Discuss
Answer: (b).Finish-to-finish (FF)
Q8.
Which of the project management charts is most effective when you want to study the relationships between tasks?
Discuss
Answer: (d).PERT chart
Q9.
Which of the following is the estimated amount of time required to complete a task, based on a weighted average of pessimistic, optimistic, and expected duration?
Discuss
Answer: (d).most likely duration
Discuss
Answer: (d).recruit team members with extensive systems development experience

Suggested Topics

Are you eager to expand your knowledge beyond Systems Analysis and Design Methods? We've curated a selection of related categories that you might find intriguing.

Click on the categories below to discover a wealth of MCQs and enrich your understanding of Computer Science. Happy exploring!