Question

Which of the project management charts is most effective when you want to study the relationships between tasks?

a.

Gantt chart

b.

PMBOK chart

c.

WBS chart

d.

PERT chart

Answer: (d).PERT chart

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Which of the project management charts is most effective when you want to study the relationships between tasks?

Similar Questions

Discover Related MCQs

Q. Which of the following is the estimated amount of time required to complete a task, based on a weighted average of pessimistic, optimistic, and expected duration?

Q. All of the following are the guidelines for selecting and recruiting team members, except

Q. A model-based technique for estimation wherein standard parameters based on prior projects are applied to the new project is known as

Q. The step-by-step instructions that solve a problem are called _____.

Q. The records in a file or magnetic tape

Q. The starting point for development of an MIS is;

Q. A Ring, refers to a record chain, the last of which refers to the first record, in the chain, is called a/an

Q. Indexed-Sequential organization

Q. Elapsed time, between initiating a query and receiving a response is called

Q. Direct-access organization

Q. A group of related fields, is known as

Q. In the system concepts, term organization

Q. Most algorithms follow the format of

Q. A Pseudocode is

Q. Pointers are useful in

Q. The Turnaround is

Q. Which of the following is (are) the characteristic(s) of a system?

Q. Announcement of MIS implementation is made by

Q. The outstanding Invoice file should be stared on a Pardon Access Storage Device if

Q. Which of the following statements is true