adplus-dvertising
frame-decoration

Question

According to Putnam's model, at what point in time does the Rayleigh curve assume its maximum value?

a.

At the beginning of the project

b.

At the point in time when the software is delivered to the customer

c.

At the end of the maintenance phase

d.

At the mid-point of the project

Answer: (b).At the point in time when the software is delivered to the customer Explanation:Putnam's model is based on Norden's finding that the distribution of manpower over time in software development projects often has a characteristic shape that is well-approximated by a Rayleigh distribution. Putnam's model defines the point in time at which the Rayleigh curve assumes its maximum value as T, which is close to the point in time at which the software is being delivered to the customer.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. According to Putnam's model, at what point in time does the Rayleigh curve assume its maximum value?

Similar Questions

Discover Related MCQs

Q. What is the main limitation of Putnam's model ?

Q. What is the main goal of function point analysis (FPA)?

Q. In which type of projects is FPA particularly suitable?

Q. How many entities play a central role in the FPA-model?

Q. What is the formula used to calculate the number of function points in FPA?

Q. What is the main advantage of using Function Point Analysis (FPA) over other cost estimation methods?

Q. What is the purpose of applying corrections to reflect differences in complexity of the data types in FPA?

Q. What is the formula used to convert the total degree of influence to a technical complexity factor in FPA?

Q. What is the unadjusted function point measure adjusted by in the FPA model?

Q. How is the adjusted function point measure obtained in the FPA model?

Q. How does the IFPUG help with counting function points in a uniform way in FPA?

Q. What are some of the problems with FPA's handling of complexity?

Q. How is the degree of influence of each characteristic in the FPA model valued?

Q. What is the main purpose of COCOMO 2?

Q. What are the three models provided by COCOMO 2?

Q. What is the basis of the Application Composition model in COCOMO 2?

Q. What is the main difference between Function Points used in FPA and Object Points used in the Application Composition model of COCOMO 2?

Q. What is the main advantage of Object Points over Function Points?

Q. What is the main use of the Application Composition model in COCOMO 2?

Q. How is the complexity level of each screen and report determined in the Application Composition model?