What is the problem with using lines of code as a measure for software size in cost estimation?

a.

It is too inexact to act as a base for a cost estimate

b.

It does not take into account the complexity and management control of the project

c.

It is not reliable early on in the project

d.

All of the above

Posted under Software Engineering

Answer: (a).It is too inexact to act as a base for a cost estimate Explanation:Using the number of lines of code as a measure for software size is too inexact to provide a reliable cost estimate early on in a project.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the problem with using lines of code as a measure for software size in cost estimation?

Similar Questions

Discover Related MCQs

Q. What is the solution to the problem of unreliable software size estimates early on in a project?

Q. What is the main problem with existing algorithmic models for cost estimation?

Q. What is the base equation of Walston and Felix's model?

Q. How many factors does the Walston and Felix model consider?

Q. What are the values that the variables Xi can take on in the Walston and Felix model?

Q. What is the approach taken by Walston and Felix for their model?

Q. What is the reason for the wide-ranging results obtained by Walston and Felix's model?

Q. What are the three classes of project that COCOMO model distinguishes?

Q. What is the formula that relates effort to software size in Basic COCOMO?

Q. What is the value of b for organic projects in COCOMO?

Q. How does the constant 'c' impact the estimate obtained in COCOMO model?

Q. How accurate are the results of the Basic COCOMO model?

Q. How does the Intermediate COCOMO model compare to the Basic COCOMO model in terms of accuracy?

Q. What is a major advantage of COCOMO?

Q. Which of the following is not a class of project in COCOMO?

Q. How many cost drivers are considered in the Intermediate COCOMO model?

Q. How does the complexity of the software impact the estimate obtained in COCOMO?

Q. What is the primary advantage of the COCOMO model?

Q. What is the shape of the distribution of manpower over time in software development projects found by Norden?

Q. According to Putnam's model, at what point in time does the Rayleigh curve assume its maximum value?