What is the example of an approach to identifying reasons for delay in software development?

a.

Empirical study of reasons for delay in software development

b.

Comparison of planned and actual figures

c.

Discussions with project leaders and department manager

d.

All of the above

Posted under Software Engineering

Answer: (d).All of the above Explanation:An example of an approach to identifying reasons for delay in software development which includes an empirical study of reasons for delay in software development, comparison of planned and actual figures, and discussions with project leaders and department manager. The study collected data relating to time and effort and identified specific reasons for delay in the environment.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the example of an approach to identifying reasons for delay in software development?

Similar Questions

Discover Related MCQs

Q. What are the steps in discovering opportunities for process improvement in an organization?

Q. What is the example of a problem that could occur if a simple approach like imposing an upperbound on the complexity allowed for each component is applied?

Q. What is the importance of having sound hypotheses while interpreting the data collected?

Q. What should the development organization do to actively produce quality software products?

Q. What are the alternatives to CMM's original levels of maturity?

Q. How does CMM compare to BOOTSTRAP and SPICE?

Q. What are the demands on the reliability of maturity assessments according to CMM?

Q. What is the implication of maturity assessments according to CMM?

Q. How does CMM's original levels compare to an instrument panel of an airplane?

Q. What is the consequence of the rather crude assessment of organizations on a five-point scale?

Q. What is the issue with CMM's original maturity levels?

Q. How does the dichotomy between factory-like and craft-like aspects of software engineering relate to CMM?

Q. What is the focus of CMM?

Q. Does the Personal Software Process (PSP) alleviate the criticism of CMM for small companies?

Q. Is the SEI's Capability Maturity Model appropriate for small companies?

Q. What is the danger of organizations focusing on obtaining CMM or ISO 9000 certification?

Q. What is the focus of SPICE?

Q. What is the focus of BOOTSTRAP?

Q. What are the basic principles of CMM and PSP?

Q. What is the first step in the PSP?