What are the process areas that must be in place to achieve a certain maturity level in CMM?

a.

Project planning

b.

Project monitoring and control

c.

Supplier agreement management

d.

All of the above

Posted under Software Engineering

Answer: (d).All of the above Explanation:To achieve a certain maturity level in CMM, a number of process areas must be in place. These process areas indicate important issues that have to be addressed in order to reach that level. These process areas include Requirements management, Project planning, Project monitoring and control, Supplier agreement management and Measurement and analysis.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What are the process areas that must be in place to achieve a certain maturity level in CMM?

Similar Questions

Discover Related MCQs

Q. What is the final maturity level in CMM?

Q. How does CMM help organizations improve the software development process?

Q. What is the main difference between the initial process level and the repeatable process level in CMM?

Q. What are the process areas needed to advance from the initial process level to the repeatable process level in CMM?

Q. What is the focus of the process area "Product integration" in CMM?

Q. What is the purpose of "Organization process focus" in CMM?

Q. What is the main goal of the organizational process definition process area in the defined process level of CMM?

Q. In CMM, at what maturity level does the organization operate without formalized procedures, project plans, or cost estimates?

Q. At what maturity level does the organization have control over costs, schedules, and change requests?

Q. What is the main focus of the organizational process definition process area in CMM?

Q. What is the purpose of the organizational training process area in CMM?

Q. What is the goal of the process area "Verification" in the repeatable process level of CMM?

Q. What is the purpose of the process area "Organizational process definition" in the defined process level of CMM?

Q. What is the focus of quantitatively managed process level?

Q. What is the focus of the optimizing process level?

Q. What is the focus of organizational innovation and deployment?

Q. What is the focus of causal analysis and resolution?

Q. What is the focus of technical improvements?

Q. How does process improvement relate to the software development process?

Q. What was the state of software engineering practice according to Humphrey's study in 1989?