adplus-dvertising
frame-decoration

Question

In CMM, at what maturity level does the organization operate without formalized procedures, project plans, or cost estimates?

a.

Initial

b.

Repeatable

c.

Defined

d.

Managed

Posted under Software Engineering

Answer: (a).Initial Explanation:At the initial process level, the organization operates without formalized procedures, project plans, or cost estimates.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. In CMM, at what maturity level does the organization operate without formalized procedures, project plans, or cost estimates?

Similar Questions

Discover Related MCQs

Q. At what maturity level does the organization have control over costs, schedules, and change requests?

Q. What is the main focus of the organizational process definition process area in CMM?

Q. What is the purpose of the organizational training process area in CMM?

Q. What is the goal of the process area "Verification" in the repeatable process level of CMM?

Q. What is the purpose of the process area "Organizational process definition" in the defined process level of CMM?

Q. What is the focus of quantitatively managed process level?

Q. What is the focus of the optimizing process level?

Q. What is the focus of organizational innovation and deployment?

Q. What is the focus of causal analysis and resolution?

Q. What is the focus of technical improvements?

Q. How does process improvement relate to the software development process?

Q. What was the state of software engineering practice according to Humphrey's study in 1989?

Q. How long does it take to move up a level in a software process improvement program?

Q. What is the cost range of a software process improvement program per employee per year?

Q. What is the Personal Software Process (PSP)?

Q. What is the first step in the PSP?

Q. What are the basic principles of CMM and PSP?

Q. What is the focus of BOOTSTRAP?

Q. What is the focus of SPICE?

Q. What is the danger of organizations focusing on obtaining CMM or ISO 9000 certification?