adplus-dvertising
frame-decoration

Question

Arrange the tasks involved in requirements elicitation in an appropriate manner.
i. Consolidation
ii. Prioritization
iii. Requirements Gathering
iv. Evaluation

a.

iii, i, ii, iv

b.

iii, iv, ii, i

c.

iii, ii, iv, i

d.

ii, iii, iv, i

Posted under Software Engineering

Answer: (b).iii, iv, ii, i

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Arrange the tasks involved in requirements elicitation in an appropriate manner. i. Consolidation ii. Prioritization iii. Requirements Gathering iv. Evaluation

Similar Questions

Discover Related MCQs

Q. What are the types of requirement in Quality Function Deployment(QFD) ?

Q. What kind of approach was introduced for elicitation and modelling to give a functional view of the system ?

Q. What are the kinds of actors used in OOSE ?

Q. Why is Requirements Elicitation a difficult task ?

Q. What requirement gathering method developed at IBM in 1970s is used for managing requirement elicitation ?

Q. How many Scenarios are there in elicitation activities ?

Q. Which of the following elicitation techniques is a view-point based method ?

Q. ___________ and ____________ are the two view points discussed in Controlled Requirements Expression (CORE).

Q. What is the major drawback of CORE(Controlled Requirements Expression) ?

Q. Choose a framework that corresponds to Issue Based Information System (IBIS).

Q. How is CORE different from IBIS ?

Q. Which of the following Requirement Elicitation Techniques removes the poor understanding of application domain and lack of common terminology between the users and the analysts ?

Q. How many steps are involved in Feature Oriented Domain Analysis (FODA) ?

Q. Which one of the following is not an actor in JAD sessions ?

Q. What of the following is not an output of a JAD session ?

Q. How is throwaway prototype different from evolutionary prototype ?

Q. Keeping the requirements of QFD in mind which of the following is not an example of an Expected Requirement ?

Q. Which of the following Requirement Elicitation Techniques is applicable to messy, changing and ill-defined problem situations ?

Q. Choose the disadvantage of using SSM as an elicitation technique.

Q. Who controls the FAST (Facilitated Application Specification Techniques) meeting ?