___________ and ____________ are the two view points discussed in Controlled Requirements Expression (CORE).

a.

Functional, Non-Functional

b.

User, Developer

c.

Known, Unknown

d.

None of the above

Posted under Software Engineering

Answer: (a).Functional, Non-Functional

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. ___________ and ____________ are the two view points discussed in Controlled Requirements Expression (CORE).

Similar Questions

Discover Related MCQs

Q. What is the major drawback of CORE(Controlled Requirements Expression) ?

Q. Choose a framework that corresponds to Issue Based Information System (IBIS).

Q. How is CORE different from IBIS ?

Q. Which of the following Requirement Elicitation Techniques removes the poor understanding of application domain and lack of common terminology between the users and the analysts ?

Q. How many steps are involved in Feature Oriented Domain Analysis (FODA) ?

Q. Which one of the following is not an actor in JAD sessions ?

Q. What of the following is not an output of a JAD session ?

Q. How is throwaway prototype different from evolutionary prototype ?

Q. Keeping the requirements of QFD in mind which of the following is not an example of an Expected Requirement ?

Q. Which of the following Requirement Elicitation Techniques is applicable to messy, changing and ill-defined problem situations ?

Q. Choose the disadvantage of using SSM as an elicitation technique.

Q. Who controls the FAST (Facilitated Application Specification Techniques) meeting ?

Q. Arrange the steps in order to represent the conducting of Wideband Delphi Technique.
i. Conduct a group discussion
ii. Conduct another group discussion
iii. Present experts with a problem
iv. Collect expert opinion anonymously
v. Iterate until consensus is reached
vi. Feedback a summary of result to each expert

Q. Which of the following is not a diagram studied in Requirement Analysis ?

Q. How many feasibility studies is conducted in Requirement Analysis ?

Q. How many phases are there in Requirement Analysis ?

Q. Requirements analysis is critical to the success of a development project.

Q. _________ and _________ are the two issues of Requirement Analysis.

Q. The requirements that result from requirements analysis are typically expressed from one of three perspectives or views. What is that perspective or view ?

Q. Coad and Yourdon suggested _______ selection characteristics that should be used as an analyst considers each potential object for inclusion in the requirement analysis model.