Question

The spiral model of software development

a.

Ends with the delivery of the software product

b.

Is more chaotic than the incremental model

c.

Includes project risks evaluation during each iteration

d.

All of the above

Answer: (c).Includes project risks evaluation during each iteration

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. The spiral model of software development

Similar Questions

Discover Related MCQs

Q. The concurrent development model is

Q. The component-based development model is

Q. The formal methods model of software development makes use of mathematical methods to

Q. Which of these is not one of the phase names defined by the Unified Process model for software development?

Q. Which of the following is not necessary to apply agility to a software process?

Q. How do you create agile processes to manage unpredictability?

Q. Which of the following traits need to exist among the members of an agile software team?

Q. What are the four framework activities found in the Extreme Programming (XP) process model?

Q. What are the three framework activities for the Adaptive Software Development (ASD) process model?

Q. Which is not one of the key questions that is answered by each team member at each daily Scrum meeting?

Q. Agile Modeling (AM) provides guidance to practitioner during which of these software tasks?

Q. The largest percentage of total life cycle cost of software is:

Q. The most creative and challenging phase of system life cycle is

Q. The advantages of creating a prototype are

Q. The main activity of the design phase of the system life cycle is to

Q. The main purpose of the system investigation phase is to produce

Q. A system analyst does not need to consider

Q. A feasibility study

Q. The combination of the top-down and the bottom-up approach may be referred to as an

Q. System prototyping helps the designer in