adplus-dvertising

Welcome to the Planning and Project Management MCQs Page

Dive deep into the fascinating world of Planning and Project Management with our comprehensive set of Multiple-Choice Questions (MCQs). This page is dedicated to exploring the fundamental concepts and intricacies of Planning and Project Management, a crucial aspect of Data Warehousing and OLAP. In this section, you will encounter a diverse range of MCQs that cover various aspects of Planning and Project Management, from the basic principles to advanced topics. Each question is thoughtfully crafted to challenge your knowledge and deepen your understanding of this critical subcategory within Data Warehousing and OLAP.

frame-decoration

Check out the MCQs below to embark on an enriching journey through Planning and Project Management. Test your knowledge, expand your horizons, and solidify your grasp on this vital area of Data Warehousing and OLAP.

Note: Each MCQ comes with multiple answer choices. Select the most appropriate option and test your understanding of Planning and Project Management. You can click on an option to test your knowledge before viewing the solution for a MCQ. Happy learning!

Planning and Project Management MCQs | Page 9 of 10

Explore more Topics under Data Warehousing and OLAP

Q81.
What is the primary focus when analyzing the details of a real-world successful project?
Discuss
Answer: (c).Specific success factors Explanation:When analyzing a real-world successful project, the primary focus is on specific success factors.
Discuss
Answer: (c).Balance between significant and less important activities Explanation:A practical approach in managing a data warehouse project emphasizes balancing significant activities against less important ones.
Discuss
Answer: (d).Minimizing wait times for dependent tasks Explanation:One of the tips for adopting a practical approach in a data warehouse project is minimizing wait times for dependent tasks.
Discuss
Answer: (b).Results, usefulness, and ease of use Explanation:Users are attracted to a data warehouse by the results, usefulness, and ease of use.
Q85.
What should you establish up front to manage user expectations realistically?
Discuss
Answer: (a).Well-defined, agreed business value Explanation:To manage user expectations realistically, you should establish well-defined, agreed business value up front.
Discuss
Answer: (c).Setting proper expectations, assessing risks, and choosing vendor solutions Explanation:Key issues to consider when planning for a data warehouse include setting proper expectations, assessing risks, and choosing from vendor solutions.
Q87.
What must drive a data warehouse project?
Discuss
Answer: (c).Business requirements Explanation:Business requirements, not technology, must drive a data warehouse project.
Q88.
What is the consequence of a data warehouse project lacking full support from top management and an enthusiastic executive sponsor?
Discuss
Answer: (d).Project doomed to failure from day one Explanation:A data warehouse project without full top management support and an enthusiastic executive sponsor is doomed to failure from day one.
Discuss
Answer: (c).After users put it to full use Explanation:Benefits from a data warehouse typically accrue after users put it to full use.
Q90.
Why is user participation considered mandatory for the success of a data warehouse project?
Discuss
Answer: (d).To ensure project success Explanation:User participation is considered mandatory to ensure the success of a data warehouse project.