In the fixed staff and variable schedule scheme, what is fixed in advance?

a.

The number of people available for the maintenance work

b.

The release date

c.

The portfolio of change requests to be handled in the next release

d.

The contents of the next release

Posted under Software Engineering

Answer: (b).The release date Explanation:In the fixed staff and variable schedule scheme, the release date is fixed in advance, and there is a fixed number of people available for the maintenance work. The contents of the next release are not fixed in advance.