What are the four framework activities found in the Extreme Programming (XP) process model?

a.

analysis, design, coding, testing

b.

planning, analysis, design, coding

c.

planning, analysis, coding, testing

d.

planning, design, coding, testing

Answer: (d).planning, design, coding, testing

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What are the four framework activities found in the Extreme Programming (XP) process model?

Similar Questions

Discover Related MCQs

Q. What are the three framework activities for the Adaptive Software Development (ASD) process model?

Q. Which is not one of the key questions that is answered by each team member at each daily Scrum meeting?

Q. Agile Modeling (AM) provides guidance to practitioner during which of these software tasks?

Q. The largest percentage of total life cycle cost of software is:

Q. The most creative and challenging phase of system life cycle is

Q. The advantages of creating a prototype are

Q. The main activity of the design phase of the system life cycle is to

Q. The main purpose of the system investigation phase is to produce

Q. A system analyst does not need to consider

Q. A feasibility study

Q. The combination of the top-down and the bottom-up approach may be referred to as an

Q. System prototyping helps the designer in

Q. Mistakes made in the system analysis stage show up in

Q. Which of the following is not true of the conversion phase of the development life cycle?

Q. Which of the following is not a factor in the failure of the systems development projects ?

Q. In phase 1 of the system development life cycle, which of the following aspects are usually analyzed?

Q. The feasibilities studied in preliminary investigation is (are)

Q. To which phase of SDLC, is file conversion related?

Q. Which of the following activities does not belong to the Implementation phase of the SDLC?

Q. A pseudocode is a/an