What is the stop criteria based on in the destruction-oriented model?

a.

Test budget running out

b.

All test cases yielding a successful result

c.

Test adequacy criterion corresponding to the test technique used

d.

100% of the branches are covered by the test cases

Posted under Software Engineering

Answer: (c).Test adequacy criterion corresponding to the test technique used Explanation:The stop criteria in the destruction-oriented model is based on the test adequacy criterion that corresponds to the test technique used. The destruction-oriented model usually entails some systematic way of deriving test cases. We may then base our stop criterion on the test adequacy criterion that corresponds to the test technique used.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the stop criteria based on in the destruction-oriented model?

Similar Questions

Discover Related MCQs

Q. What is the main focus of the evaluation-oriented model?

Q. What is the main focus of the prevention model?

Q. What is the main idea behind test-driven development?

Q. What is the gradual shift of emphasis in test practice?

Q. What is the role of testing in an improvement process?

Q. What is the main focus of software developers?

Q. What is the approach of Test-driven Development (TDD)?

Q. What is the focus of verification and validation activities during software development?

Q. What is the purpose of requirements engineering?

Q. What are the criteria for a requirements specification according to Boehm?

Q. What is the main aim of testing the completeness criterion of a requirements specification?

Q. What is the purpose of testing the requirements specification?

Q. What are the four essential criteria for a requirements specification according to Boehm?

Q. What does the feasibility criterion have to do with?

Q. What are the most likely errors in a requirements specification according to Poston?

Q. What is the purpose of a standard format for documenting the requirements specification?

Q. What is the most likely error in a requirements specification according to Poston?

Q. What is the purpose of using a standard format for documenting the requirements specification?

Q. What is the purpose of the design phase?

Q. What is the purpose of testing the design itself during the design phase?