adplus-dvertising
frame-decoration

Question

What is the goal of planning meetings in Extreme Programming?

a.

To deliver the immediate functionality to the customer

b.

To design a grand scheme

c.

To implement a story

d.

To remove duplicate code

Answer: (a).To deliver the immediate functionality to the customer Explanation:In Extreme Programming, planning meetings are very short and involve the immediate functionality to be delivered to the customer. Planning involves both the customer and the technical people.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the goal of planning meetings in Extreme Programming?

Similar Questions

Discover Related MCQs

Q. In XP, what is the practice of two programmers working together behind one computer screen called?

Q. In XP, what is the practice of removing complexity from the design as soon as possible called?

Q. In XP, what is the practice of integrating and building the system many times a day called?

Q. In XP, what is the practice of having a real user on the team full-time called?

Q. In XP, what is the practice of establishing coding standards to ease communication called?

Q. What are the five principles that drive XP practices?

Q. What is the main goal of XP?

Q. What is the practice of having two programmers work together on one computer screen called?

Q. What is the practice of continuously testing the system after each component is written called?

Q. What is the main goal of the inception phase in RUP?

Q. How many phases does RUP distinguish?

Q. In RUP, what is the main focus of the construction phase?

Q. What is the main benefit of RUP?

Q. Which of the following is not a workflow in RUP?

Q. What is the main focus of RUP's construction phase?

Q. What is the main goal of RUP's inception phase?

Q. What is the main goal of RUP's elaboration phase?

Q. What is the main goal of RUP's transition phase?

Q. What is the main difference between maintenance and initial development of a system?

Q. How does time pressure affect maintenance activities?