What is the relationship between the size of a system and the time needed to build it?

a.

Larger systems require less time to develop

b.

Larger systems require more time to develop

c.

The size of a system has no effect on the time needed to build it

d.

It depends on the complexity of the system

Posted under Software Engineering

Answer: (b).Larger systems require more time to develop Explanation:The time needed to build a system is obviously related to the size of the system, and thus to the total manpower required. Larger systems require more time to develop.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. What is the relationship between the size of a system and the time needed to build it?

Similar Questions

Discover Related MCQs

Q. Adding more people to a software development project:

Q. What is the main problem associated with controlling time in software development projects?

Q. According to Brooks’ Law, what happens when more people are added to a late project?

Q. What is the most important information that needs to be managed in a software development project?

Q. What is the main goal of quality assurance in software development?

Q. What is the main problem of controlling time in software development project?

Q. What is the main type of information that has to be managed during the software development project?

Q. What are the main aspects of the control during the software development project?

Q. What is the main goal of the quality assurance during the software development project?

Q. What is the main way of controlling expenses during the software development project?

Q. What are the main factors that influence the cost of software development?

Q. What is the importance of data collection in the software development process?

Q. Which of the following is not a control dimension for a software development project?

Q. According to Brooks' Law, what happens when more people are added to a late project?

Q. Which phase of software development process is the most labor-intensive?

Q. In which phase of software development process is the quality aspect most important?

Q. What is the main purpose of post-mortem evaluation of the project?

Q. What is the main purpose of Configuration Management?

Q. What are some of the different versions of a software system that may exist during development?

Q. What is an example of a product line in software development?