On an average, the programmes months is given by 3.6 x (KDSI)¹·². If so a project requiring one Thousand source instructions will require

a.

3.6 PM

b.

0.36 PM

c.

0.0036 PM

d.

7.23 PM

Answer: (a).3.6 PM