Question

Which of following changeover method is said to be most expensive?

a.

Parallel Run

b.

Phased conversion

c.

Immediate changeover

d.

Process conversion

Posted under IT Fundamentals

Answer: (a).Parallel Run

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Which of following changeover method is said to be most expensive?

Similar Questions

Discover Related MCQs

Q. When available manpower is limited, preferred method of changeover to apply is of

Q. To carry out change process, followed methods are said to be of

Q. Most safest way to deploy a new system is by method of

Q. When available changeover time is less, suitable changeover method to apply is of

Q. New system is put to operation from a decided suitable cut off date in changeover method known as

Q. New system must not differ from old system to a great extend in process of

Q. Communication takes place in only one direction in communication mode of

Q. Basic elements of any communication system includes a sender, receiver and

Q. Basic models for transmission of data from one to another, can be classified into

Q. Data handling capacity of a communication system is known to be

Q. Available range of frequencies for transmission of data is termed as

Q. Communication mode in which data can be transmitted in both directions but in one direction at a time is known to be

Q. Data redundancy results in increase cost of

Q. Consistency of data in all files represents

Q. In file-oriented approach, query can be processed quickly, if records are stored with

Q. When there's a need to update data, application program must also be updated because of

Q. Repetition of same data items in more than one file can create

Q. Data being dependent on an application represents its

Q. Multiple related fields are combined to make a

Q. A series of operations or actions to convert some input to useful output is known to be