Critical path of the PERT chart is:

a.

path which takes the longest time to complete the project

b.

the shortest path

c.

both of the above

d.

path which takes the shortest time to complete the project

Answer: (a).path which takes the longest time to complete the project

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Critical path of the PERT chart is:

Similar Questions

Discover Related MCQs

Q. A _____ is a brief message to an operator that describes what data are to be entered.

Q. Educational programs for the labour union officials are conducted by

Q. If you are an information-system manager, which organization is most appropriate for your interest?

Q. The four major corporate resources are money, materials, information, and

Q. Which of the following is(are) true of system analysts?

Q. From a data systems design viewpoint, the number of different types of general ledger entries is

Q. External data is stored in the

Q. An example of a management by exception report is a(n)

Q. The major function of the language system is:

Q. One of the purchases order system's procedure sets is

Q. The functional area showing the greatest interest in the concept of functional information systems is the

Q. A turnaround document can be a (n)

Q. The manager attempts to slow down the flow of

Q. The accident file is commonly updated in the

Q. General ledger is also referred to as:

Q. The subsystem appearing in each of the functional information systems is the

Q. A chart comprised of bars, each representing a period of time, is called a

Q. Corporate modeling languages often do provide for

Q. Which of the following is(are) true concerning information-system careers?

Q. When purchase cost is $20, maintenance cost is $0.50, and annual sale are 20 units, EOQ is