adplus-dvertising
frame-decoration

Question

 From the following give three major categories of risk,
1) Schedule risk
2) Project risk
3) Technical risk
4) Business risk

a.

1,2 and 3

b.

2,3 and 4

c.

1,2 and 4

d.

1,3 and 4

Answer: (b).2,3 and 4

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q.  From the following give three major categories of risk, 1) Schedule risk 2) Project risk 3) Technical risk 4) Business risk

Similar Questions

Discover Related MCQs

Q. In Risk management process what makes a note of all possible risks, that may occur in the project?

Q. Which risks identify Potential Design, Implementation, Interface, Verification and Maintenance Problems?

Q. Building an excellent product or system that no one really want a risk is a
________ .

Q. Which is the characteristics of Software risk?

Q. What all has to be identified as per risk identification?

Q. Which one is not a risk management activity?

Q. What is the product of the probability of incurring a loss due to the risk and the potential magnitude of that loss?

Q. What threatens the quality and timeliness of the software to be produced?

Q. What threatens the viability of the software to be built?

Q. Which of the following is not a business risk?

Q. Which of the following is a systematic attempt to specify threats to the project plan?

Q. Which risks are associated with the overall size of the software to be built or modified?

Q. Which risks are associated with constraints imposed by management or the marketplace?

Q. Which of the following term is best defined by the statement:”the degree of uncertainty that the product will meet its requirements and be fit for its intended use.”?

Q. Risk management is one of the most important jobs for a

Q. Which of the following risk is the failure of a purchased component to perform as expected?

Q. Which of the following term is best defined by the statement: “There will be a change of organizational management with different priorities.”?

Q. Which of the following term is best defined by the statement: “The underlying technology on which the system is built is superseded by new technology.”?

Q. What assess the risk and your plans for risk mitigation and revise these when you learn more about the risk?

Q. Which of the following risks are derived from the organizational environment where the software is being developed?