Question
(Where: BCWP stands for Budgeted Cost of Work Performed
BCWS stands for Budget Cost of Work Scheduled
ACWP stands for Actual Cost of Work Performed)
a.
BCWP/ACWP
b.
BCWP−ACWP
c.
BCWP−BCWS
d.
None of the above
Engage with the Community - Add Your Comment
Confused About the Answer? Ask for Details Here.
Know the Explanation? Add it Here.
Q. Software Cost Performance index (CPI) is given by: (Where: BCWP stands for Budgeted Cost of Work Performed BCWS stands for Budget Cost of Work Scheduled ACWP stands for...
Similar Questions
Discover Related MCQs
Q. Software Risk estimation involves following two tasks:
View solution
Q. In a object oriented software design, ‘Inheritance’ is a kind of...................
View solution
Q. Reliability of software is directly dependent on:
View solution
Q. ‘Abstraction’ is......................step of Attribute in a software design.
View solution
Q. In software project planning, work Breakdown structure must be .................
View solution
Q. In Software Metrics, McCABE’s cyclomatic number is given by following formula:
View solution
Q. In a good software design, ................ coupling is desirable between modules.
View solution
Q. System study yields the following:
View solution
Q. The COCOMO model is used for ..................
View solution
Q. The testing of software against SRS is called:
View solution
Q. The lower degree of cohesion is:
View solution
Q. The reliability of the software is directly dependent upon:
View solution
Q. Successive layer of design in software using bottom-up design is called:
View solution
Q. Sliding window concept of software project management is:
View solution
Q. A black hole in a DFD is a:
View solution
Q. The capability maturity model (err) defines 5 levels:
(a) Level 1 (i) Managed
(b) Level 2 (ii) Defined
(c) Level 3 (iii) Repeatable
(d) Level 4 (iv) Initial
(e) Level 5 (v) Optimized
correct matching is:
a b c d e
View solution
Q. Which one of the following is not a software process model ?
View solution
Q. System Development Life-cycle has following stages:
(I) Requirement analysis (II) Coding
(III) Design (IV) Testing
Which option describes the correct sequence of stages?
View solution
Q. Which one is measure of software complexity ?
View solution
Q. Which type of coupling is least preferred ?
View solution
Suggested Topics
Are you eager to expand your knowledge beyond Software Engineering? We've curated a selection of related categories that you might find intriguing.
Click on the categories below to discover a wealth of MCQs and enrich your understanding of Computer Science. Happy exploring!