adplus-dvertising
frame-decoration

Question

Software Cost Performance index (CPI) is given by:

(Where:   BCWP stands for Budgeted Cost of Work Performed
BCWS stands for Budget Cost of Work Scheduled
ACWP stands for Actual Cost of Work Performed)

a.

BCWP/ACWP

b.

BCWP−ACWP

c.

BCWP−BCWS

d.

None of the above

Answer: (a).BCWP/ACWP

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Software Cost Performance index (CPI) is given by: (Where:   BCWP stands for Budgeted Cost of Work Performed BCWS stands for Budget Cost of Work Scheduled ACWP stands for...

Similar Questions

Discover Related MCQs

Q. Software Risk estimation involves following two tasks:

Q. In a object oriented software design, ‘Inheritance’ is a kind of...................

Q. Reliability of software is directly dependent on:

Q. ‘Abstraction’ is......................step of Attribute in a software design.

Q. In software project planning, work Breakdown structure must be .................

Q. In Software Metrics, McCABE’s cyclomatic number is given by following formula:

Q. In a good software design, ................ coupling is desirable between modules.

Q. System study yields the following:

Q. The COCOMO model is used for ..................

Q. The testing of software against SRS is called:

Q. The lower degree of cohesion is:

Q. The reliability of the software is directly dependent upon:

Q. Successive layer of design in software using bottom-up design is called:

Q. Sliding window concept of software project management is:

Q. A black hole in a DFD is a:

Q. The capability maturity model (err) defines 5 levels:

(a) Level 1         (i) Managed
(b) Level 2         (ii) Defined
(c) Level 3         (iii) Repeatable
(d) Level 4         (iv) Initial
(e) Level 5         (v) Optimized

correct matching is:
   a     b    c     d     e

Q. Which one of the following is not a software process model ?

Q. System Development Life-cycle has following stages:

(I) Requirement analysis        (II) Coding
(III) Design                    (IV) Testing

Which option describes the correct sequence of stages?

Q. Which one is measure of software complexity ?

Q. Which type of coupling is least preferred ?