Question

Software risk estimation involves following two tasks :

a.

Risk magnitude and risk impact

b.

Risk probability and risk impact

c.

Risk maintenance and risk impact

d.

Risk development and risk impact

Answer: (b).Risk probability and risk impact

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. Software risk estimation involves following two tasks :

Similar Questions

Discover Related MCQs

Q. Enterprise Resource Planning (ERP)

Q. Which of the following is false concerning Enterprise Resource Planning (ERP)?

Q. Which one of the items listed below is not one of the software engineering layers ?

Q. What is the first stage in program development ?

Q. By means of a data flow diagram, the analyst can detect

Q. Which of these are the 5 generic software engineering framework activities ?

Q. Many causes of the software crisis can be traced to mythology based on

Q. “Black” refers in the “Black-box” testing means

Q. In generalisation, the differences between members of an entity is

Q. Prototyping is used to

Q. Which one of these are not software maintenance activity?

Q. The system specification is the first deliverable in the computer system engineering process which does not include

Q. The COCOMO model was introduced in the book title “Software Engineering Economics” authored by

Q. The Warnier diagram enables analyst

Q. Software engineering primarily aims on

Q. Top-down design does not require

Q. Which model is simplest model in Software Development?

Q. Design phase will usually be

Q. Software Engineering is a discipline that integrates ………….. for the development of computer software.

Q. Any error whose cause cannot be identified anywhere within the software system is called …………..