Question

The expected value for the estimation variable (size), S, can be computed as a weighted average of the optimistic(Sopt), most likely (Sm), and pessimistic (Spess) estimates given as

a.

EV = (Sopt + 4Sm + Spess)/4

b.

EV = (Sopt + 4Sm + Spess)/6

c.

EV = (Sopt + 2Sm + Spess)/6

d.

EV = (Sopt + 2Sm + Spess)/4

Answer: (b).EV = (Sopt + 4Sm + Spess)/6

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. The expected value for the estimation variable (size), S, can be computed as a weighted average of the optimistic(Sopt), most likely (Sm), and pessimistic (Spess) estimates given...

Similar Questions

Discover Related MCQs

Q. How many forms exists of Barry Boehm’s COCOMO Model?

Q. Who suggested the four different approaches to the sizing problem?

Q. In many cases, it is often more cost effective to acquire, rather than develop, computer software.

Q. A make-buy decision is based on whether

Q. Which of the following is not one of the five information domain characteristics of Function Point (FP) decomposition?

Q. The project planner must reconcile the estimates based on decomposition techniques to produce a single estimate of effort.

Q. Programming language experience is a part of which factor of COCOMO cost drivers?

Q. If an Indirect approach is taken, then the sizing approach is represented as

Q. Project management involves the planning, monitoring, and control of the people, process, and events that occur as software evolves from a preliminary concept to an operational implementation.

Q. Which of the following is not an effective software project management focus?

Q. PM-CMM stands for

Q. Which of the following is not a project manager’s activity?

Q. A software ________ provides the framework from which a comprehensive plan for software development can be established.

Q. Who defines the business issues that often have significant influence on the project?

Q. Who delivers the technical skills that are necessary to engineer a product or an application?

Q. Which of the following paradigm attempts to structure a team in a manner that achieves some of the controls associated with the closed paradigm but also much of the innovation that occurs when using the random paradigm?

Q. Which of the following is a people-intensive activity?

Q. Which paradigm structures a team loosely and depends on individual initiative of the team members?

Q. Which of the following is not an approach to software cost estimation?

Q. Which paradigm relies on the natural compartmentalization of a problem and organizes team members to work on pieces of the problem with little active communication among themselves?