adplus-dvertising
frame-decoration

Question

How is WINWIN Spiral Model different from Spiral Model?

a.

It defines tasks required to define resources, timelines, and other project related information.

b.

It defines a set of negotiation activities at the beginning of each pass around the spiral.

c.

It defines tasks required to assess both technical and management risks.

d.

It defines tasks required to construct, test, install, and provide user support.

Answer: (b).It defines a set of negotiation activities at the beginning of each pass around the spiral.

Engage with the Community - Add Your Comment

Confused About the Answer? Ask for Details Here.

Know the Explanation? Add it Here.

Q. How is WINWIN Spiral Model different from Spiral Model?

Similar Questions

Discover Related MCQs

Q. Identify the disadvantage of Spiral Model.

Q. How is Incremental Model different from Spiral Model?

Q. If you were to create client/server applications, which model would you go for?

Q. Selection of a model is based on

Q. Which two models doesn’t allow defining requirements early in the cycle?

Q. Which of the following life cycle model can be chosen if the development team has less experience on similar projects?

Q. If you were a lead developer of a software company and you are asked to submit a project/product within a stipulated time-frame with no cost barriers, which model would you select?

Q. Which two of the following models will not be able to give the desired outcome if user’s participation is not involved?

Q. A company is developing an advance version of their current software available in the market, what model approach would they prefer ?

Q. Choose the correct option from given below:

Q. Which of the following model has a major disadvantage in terms of the coding phase of a software life cycle model ?

Q. The tools that support different stages of software development life cycle are called as ______ .

Q. Find out which phase is not available in SDLC?

Q. Which SDLC activity does the user initiates the request for a desired software product?

Q. First level of prototype is evaluated by ______ .

Q. Which of the items listed below is not one of the software engineering layers?

Q. For the best Software model suitable for the project, in which of the phase the developers decide a roadmap for project plan?

Q. Where is the prototyping model of software development well suited?

Q. Design phase is followed by ______ .

Q. The two dimensions of spiral model are